Widen EB and WB SR-91 from East of SR-55 connector (Lakeview Av) to East of Weir Canyon Road |
Description: In Anaheim, from east of Route 55 connector (Lakeview Avenue) to east of Weir Canyon Road. Add one lane in each direction.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | Anaheim, Yorba Linda |
Zip Code | 92807, 92808, 92887 |
Senate District |
29, 33 |
Assembly District | 60, 71 |
Congressional District | 42 |
Caltrans District |
12 |
County/State Route | Orange 91 |
Postmile Begin/End | 9.1 15.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 31946 | 55166 |
Lane Miles Added (HOV) | 12 | |
Lane Miles Added (Mixed) | 12 | |
Peak Period Time Savings (minutes) | 2544065 | 4393265 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Adnan Maiah | (949) 724-2089 | adnan.maiah@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Adnan Maiah | (949) 724-2089 | adnan.maiah@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Adnan Maiah | (949) 724-2089 | adnan.maiah@dot.ca.gov | |
Construction Phase |
Department of Transportation | Adnan Maiah | (949) 724-2089 | adnan.maiah@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Ryan Chamberlain | (949) 724-2899 | ryan_chamberlain@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $22,107 | $22,107 | ||||
CMIA |
$17,937 | $36,108 | $54,045 | ||||
Non-bond Funding | |||||||
State/Federal* |
$74,000 | $-72,850 | $1,150 | ||||
Total**** | $91,937 | $-14,635 | $77,302 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$4,763 | $-114 | $4,649 | $4,114 | |||
Design(PS&E) |
$9,050 | $-225 | $8,825 | $7,989 | |||
Right of Way |
$3,510 | $-2,360 | $1,150 | $227 | |||
Construction |
$74,614 | $-11,936 | $62,678 | $63,966 | |||
Total* | $91,937 | $-14,635 | $77,302 | $76,296 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2007 07/01/2009 |
|
07/01/2007 07/01/2009 |
100 | 07/01/2007 04/24/2009 |
0 2 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2009 05/01/2011 |
|
07/01/2009 05/01/2011 |
100 | 05/01/2009 12/22/2010 |
2 4 |
|
Begin Right of Way Phase
End Right of Way Phase |
06/01/2009 05/01/2011 |
|
06/01/2009 05/01/2011 |
100 | 06/01/2009 09/01/2010 |
0 8 |
|
Begin Construction Phase
End Construction Phase |
12/01/2011 12/01/2014 |
|
12/01/2011 12/01/2014 |
100 | 05/03/2011 11/01/2013 |
7 13 |
|
Begin Closeout Phase
End Closeout Phase |
12/01/2014 12/01/2015 |
|
12/01/2014 12/01/2015 |
100 | 04/01/2014 05/30/2014 |
8 18 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 05/01/2009 | 05/01/2009 | 0 | 05/01/2009 | 0 | ||
Implementation Date | 06/01/2009 | 06/01/2009 | 0 | 11/16/2010 | -18 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 31946 | 55166 |
Lane Miles Added (HOV) | 12 | |
Lane Miles Added (Mixed) | 12 | |
Peak Period Time Savings (minutes) | 2544065 | 4393265 |
Bond Funding Cost | |
---|---|
Adopted: |
$17,937,000 |
Current Approved: |
$17,937,000 |
Actual Expenditures: |
$17,937,000 |
Status as of December 31, 2023.