Widen EB and WB SR-91 from East of SR-55 connector (Lakeview Av) to East of Weir Canyon Road

Description: In Anaheim, from east of Route 55 connector (Lakeview Avenue) to east of Weir Canyon Road. Add one lane in each direction.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Anaheim, Yorba Linda
Zip Code 92807, 92808, 92887
 
Senate District
29, 33
Assembly District 60, 71
Congressional District 42
 
Caltrans District
12
 
 
County/State Route Orange 91
Postmile Begin/End 9.1 15.6
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  31946    55166  
Lane Miles Added (HOV)      12  
Lane Miles Added (Mixed)  12      
Peak Period Time Savings (minutes)  2544065    4393265  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Adnan Maiah (949) 724-2089   adnan.maiah@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Adnan Maiah (949) 724-2089   adnan.maiah@dot.ca.gov
Right of Way Phase
Department of Transportation Adnan Maiah (949) 724-2089   adnan.maiah@dot.ca.gov
Construction Phase
Department of Transportation Adnan Maiah (949) 724-2089   adnan.maiah@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Ryan Chamberlain (949) 724-2899   ryan_chamberlain@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $22,107 $22,107
CMIA
$17,937 $36,108 $54,045
Non-bond Funding
State/Federal*
$74,000 $-72,850 $1,150
 
Total**** $91,937 $-14,635 $77,302

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$4,763 $-114 $4,649 $4,114
Design(PS&E)
$9,050 $-225 $8,825 $7,989
Right of Way
$3,510 $-2,360 $1,150 $227
Construction
$74,614 $-11,936 $62,678 $63,966
 
Total* $91,937 $-14,635 $77,302 $76,296

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

07/01/2009 
 

 
07/01/2007 

07/01/2009 
100  07/01/2007 

04/24/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2009 

05/01/2011 
 

 
07/01/2009 

05/01/2011 
100  05/01/2009 

12/22/2010 


Begin Right of Way Phase

End Right of Way Phase
06/01/2009 

05/01/2011 
 

 
06/01/2009 

05/01/2011 
100  06/01/2009 

09/01/2010 


Begin Construction Phase

End Construction Phase
12/01/2011 

12/01/2014 
 

 
12/01/2011 

12/01/2014 
100  05/03/2011 

11/01/2013 


13 
Begin Closeout Phase

End Closeout Phase
12/01/2014 

12/01/2015 
 

 
12/01/2014 

12/01/2015 
100  04/01/2014 

05/30/2014 


18 
Corridor System Management Plan
Adoption Date 05/01/2009    05/01/2009  05/01/2009 
Implementation Date 06/01/2009    06/01/2009  11/16/2010  -18 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 31946 55166
Lane Miles Added (HOV) 12
Lane Miles Added (Mixed) 12
Peak Period Time Savings (minutes) 2544065 4393265

Bond Funding Cost
Adopted:
$17,937,000
Current Approved:
$17,937,000
Actual Expenditures:
$17,937,000

 

Status as of December 31, 2023.